CPEC Project Details: Khuzdar-Basima Road N-30 (110 km)

Project : Khuzdar-Basima Road N-30 (110 km)
Province: Balochistan
Estimated Cost (US $ Million): 80
Project Progress: 25% Completion
Project Progress Update:
  • Feasibility and PC-I completed
  • LOI forwarded to Chinese side
  • 129 km Multan- Tranda M. Panah (Bahawalpur) section to be completed by April,2018.
  • Procedural formalities to be completed shortly (ECNEC approved the projects in May 2017)
  • Frame Work Agreement shared with Chinese Side