Recognizing the growing energy needs of Pakistan, and to overcome the existing deficits, CPEC has allocated a major proportion of its funds to energy generation and transmission.

Energy projects stated below are included in CPEC and would contribute towards the sustainable growth of industries and unhindered electric supply for domestic consumption in Pakistan.

Prioritized/Early Harvest Projects, 10400 MW

Project Name:Company Name:Status:Progress:Pictures:
2x660MW Port Qasim Coal-fired Power PlantPower China Resources Ltd.Under Construction100% Completion

2x6600MW Coal Fired Power Plant Port Qasim
2x660MW Sahiwal Coal-Fired Power PlantHuaneng Shandong Ruyi (Pakistan) Energy (Private) Ltd.Two units inaugurated100% Completion

2x660MW Coal Fired Power Plant Sahiwal
4x330MW Engro Thar Coal-fired Power Plant and Surfice Mine in Block II of Thar Coal FieldChina Machinery Engineering Corporation(CMEC)Under Construction60% Completion

4x330MW Engro Thar Coal-fired Power Plant and Surfice Mine in Block II of Thar Coal Field
50MW Dawood Wind FarmHydrochina International Engineering Co. Ltd.Commercial Operation Date achieved100% Completion

50MW Dawood Wind Farm
900MW Quaid-e-Azam Solar Park in BahawalpurZonergy Company Ltd.Energization achieved100% Completion

900MW Quaid-e-Azam Solar Park in Bahawalpur
100MW Jhimpir Wind FarmUEP Wind Power (PVT) Ltd.Under Construction
100% Completion

100MW Jhimpir Wind Farm
873MW Suki Kinari Hydropower ProjectChina Gezhouba Group Corporation International Ltd. (CGGC)Under Construction65% Completion

50MW Sachal Wind FarmChina Sunec CompanyCommercial Operation Date Achieved100% Completion

50MW Sachal Wind Farm
2x660MW Rahimyar Khan Coal Power PlantTBD (To Be Determined)Feasibility stage
15% Completion

Thar Coal Block I and 2x660MW Mine Mouth Power PlantShanghai ElectricTo be inaugurated50% Completion

Thar Coal Block I and 2x660MW Mine Mouth Power Plant
2 x 660MW Hubco Coal Power PlantChina Power International Holding Ltd.Implementation Agreement Initiated; Expected financial close by August 2017
50% Completion

300 MW Gwadar Power PlantTBD (To Be Determined)Feasibility stage60% Completion

Matiari-Lahore Transmission LineChina State GridNegotiation in Process
15% Completion

Matiari-Faisalabad Transmission LineChina State GridNegotiation in Process
15% Completion

Actively Promoted Projects, 17045 MW

Project Name:Company Name:Status:Progress:Pictures:
2x660MW Gaddani Powerplant at District Lasbela, BalochistanTBD (To Be Determined)Feasibility Stage
15% Completion

1100MW Kohala Hydro-Power StationChina Three Gorges South Asia Investment Ltd.Negotiation in Process15% Completion

2x50MW Wind Farm Phase II of PakistanChina Three Gorges South Asia Investment Ltd.Financial Close Achieved70% Completion

660MW HUBCO Coal Power Plant China Power International Holding Ltd.Negotiation in Process15% Completion

300MW Salt Range Mine Mouth Power Plant including MiningChina Machinery Engineering Corporation (CMEC)15% Completion

2x660MW Thar Mine Mouth Coal Fired Power Plant by OracleTBD (To Be Determined)Feasibility stage15% Completion

2x660MW Muzaffargarh Coal-fire Power PlantChina Machinery Engineering Corporation (CMEC)Feasibility stage15% Completion

525MW Gas Fired Power PlantTBD (To Be Determined)Feasibility stage15% Completion